Unit 3 of Nam Ou 1HPP is connected to the grid

Source: Author: Time: 2020-07-20

On July 17, 2020, at 9:30 am Lao time, the good news came from Nam Ou River Basin Cascade Hydropower Project. Unit 3 of the 1HPP phase II project was successfully connected to the grid. After the test of load dumping, it entered the 72-hour trial operation at 4:30 PM. This is the second unit connected to the grid after unit 2 on June 9, which is significance for the project to achieve the goal of full operation.