The construction and installation of the Ivovik wind farm project in Bosnia and Herzegovina has been completed
Source:
Author:
Time: 2023-11-02
On October 30, 2023, the Ivovik wind farm project in Bosnia and Herzegovina completed the wiring and static debugging of the main electrical equipment of the booster station, which marked the successful completion of the construction and installation of the entire field after 16 months of intense construction. The realization of this important milestone node means that the construction of the project has been physically completed. The project has fully entered the grid acceptance and grid-connection commissioning stage.